How the entitlement is derived

Protocol core principles applied

Head-office overheads & profit

Part C §2 · formulae, with caution

Recoverable only if the Contractor shows that overheads went unabsorbed and that other work was available (Part C §2.6–2.8). The burden stays with the Contractor; a formula quantifies, it does not prove.

Programme impact

days from the Commencement Date

Claim procedure

Today

Deadlines run from the date the Contractor became aware, or should have become aware, of the event.

What to keep from day one

1999 versus 2017

The 2017 forms bar both Parties; give the Engineer 14 days to object to a late Notice (silence deems it valid); allow 84 days for the fully detailed claim; and add the 42 + 42 day agreement and determination steps under 3.7. The 1999 forms and the MDB editions bar only the Contractor, want the fully detailed claim in 42 days and the Engineer's response in 42.

When is the EOT being assessed?

The Protocol prefers cause-and-effect methods while the works proceed (CP 4) and effect-and-cause methods once the assessment is time-distant (CP 11).

Programme on file

The Accepted / Updated Programmes of Core Principle 1 are what make the software-driven methods reliable.

As-built records

Site diaries, progress photographs, labour and plant returns, and dated correspondence (20.2.3 contemporary records).

Method choice follows Protocol §11.3: the conditions of contract, the nature of the events and of the project, proportionality to the value in dispute, the time available, the records and programme information actually held, and the forum. Whatever the method, the conclusion must be sound from a common-sense perspective (§11.2).

The 22 Core Principles

SCL Delay and Disruption Protocol, 2nd edition, February 2017 — summarised; the text itself governs