CiO LabProgramme Builder
Plan the works

Build the programme

Activities, durations and the logic that links them. The critical path, the float and the completion date are computed as you type, the programme is tested against what Sub-Clause 8.3 and the SCL Protocol expect of it, and a delay can be impacted on it to see what it does to completion.

Early and late dates come from the forward and backward pass over the working calendar. Total float is the slack before the activity delays completion; the critical path is every activity with none. Value share is optional and feeds the cost projection.

criticalwith floatprogressedimpacted positionmilestone┆ Date for Completion│ data date

Programme checks

The Protocol asks for a properly logic-linked, resourced programme, updated as the works proceed, so that delay can be measured against it (Core Principles 1 and 2). A programme that cannot pass these checks will struggle to carry a claim.

What Sub-Clause 8.3 asks for

Tick what the programme submission includes. The 2017 forms list these in Sub-Clause 8.3; the 1999 forms and the MDB editions ask for the order, the timing, the periods for reviews, the inspections and tests, and a supporting report on methods and resources.

Delay events

Each event is inserted as a fragnet against the activity it affects: either it delays the start of the activity or it prolongs the work. The programme is then re-scheduled and completion read off, which is the Time Impact Analysis the Protocol prefers for a prospective assessment (Core Principle 4). Employer and Contractor events are impacted separately so concurrency can be seen.

Take these figures to the delay check and the claim builder.
Files

The MS Project file carries the activities, durations, dates and links; Primavera P6 opens it through File › Import › Microsoft Project XML.

To the other tools

The cost projection reads the programme as phases by section: the value share you entered, spread over each section's dates. The delay check and the claim builder read the impacted completion.